In September 2019, Kinross announced it was
proceeding with the Tasiast 24k project, a capital efficient continuous
improvement project that is expected to increase Tasiast’s throughput capacity
to 21,000 t/d by the end of 2021 and 24,000 t/d by mid-2023. The project is on
budget and on schedule to be completed
by year-end 2021.
Captured above, ongoing progress of the construction of the new 40 metre ‘thickener’, which is expected to improve Tasiast’s overall water consumption!