|
McIntyre Mine Site
|
RECLAMATION OF FORMER ROYAL OAK MINE
SITES
MCINTYRE MINE SITE AND TOWNSITE DEMOLITION AND RECLAMATION
TIMMINS, ONTARIO, CANADA |
General Project Overview
In the summer of 2000, Kinross Gold Corporation initiated
progressive rehabilitation of the former Royal Oak Mines
McIntyre Mine property. The 2000-2001 project was carried out as
part of the rehabilitation work being done under a cooperative
agreement with the Ontario Ministry of Northern Development and
Mines. The reclamation work undertaken by Kinross included the
demolition of the surface infrastructure at the McIntyre Mine
and associated town site.
The
McIntyre Mine reportedly operated between 1912 and 1988 and was
once one of the largest gold producers in the world. The mine
consisted of an underground mining operation with several access
shafts and vent raises.
In 2000, all that remained of the former mine were
two headframes and associated shafts, two hoist rooms, a
refinery, storage buildings and an administration building.
Several of these buildings, including the mineshaft, presented
serious safety hazards and required to be addressed
expeditiously. A town site was also located south of the mine
and had housed employees and managers.
The 2000-2001 progressive rehabilitation of the
McIntyre property consisted of the removal of all buildings and
infrastructure surrounding the Shaft No. 11 headframe, the
demolition and capping of the Shaft No. 6 headframe, and the
recapping of the Jupiter Shaft. The removal of older foundation
remnants was not part of this initial reclamation work. The
demolition was contracted out to Lacroix Construction of
Sudbury, Ontario.
Before the demolition work began, Kinross and the
contractor prepared an action plan that would see the project
achieve fruition in early 2001.
In accordance with Kinross and provincial
environmental requirements, maximum recycling and reuse of
building materials was carried out in order to reduce material
volumes transported to an on-site landfill site. All recyclable
materials from the mine site were separated from the waste
streams and collected by local building material recyclers.
Following the removal of all wastes to the landfill site, all
remaining concrete foundations at the mine site and town site
were collapsed and buried in place as inert fill. All waste
chemicals and petroleum products encountered at the site were
gathered and removed by a licensed waste disposal company.
During the demolition of the mine site, the
existing Shaft No. 6 and Jupiter Shaft were permanently closed
with engineered reinforced concrete caps anchored into the shaft
collar or surrounding bedrock. The cap was constructed in
accordance with rehabilitation regulations set out in the
Ontario Mining Act.
Following
the removal of all non-recyclable debris, concrete foundations
and brick walls were collapsed into basements and covered with
imported overburden. All abandoned roadway surfaces, as well as
other disturbed surfaces on the mine site and within the town
site were loosened, graded, and prepared for revegetation. The
prepared areas were seeded with a mixture of seed and
fertilizer. The landfill site was also covered with new sandy
soil.
The only remaining building, following the
demolition of the mine site, was the Shaft No. 11 headframe and
a shed containing electrical switchgear for the headframe. The
headframe and its immediate surroundings will eventually be
redeveloped by the City of Timmins as a heritage monument to
gold mining in the Porcupine Camp.
A report describing the progressive rehabilitation
works was issued to the Ministry of Northern Development and
Mines in October 2001. |