|
Aunor Mine Site
|
RECLAMATION OF FORMER ROYAL OAK MINE
SITES
AUNOR MINE SITE AND TOWNSITE DEMOLITION AND RECLAMATION
TIMMINS, ONTARIO, CANADA |
General Project Overview
In
September 2000, Kinross began reclamation of the Aunor Mine and
demolition of the townsite. The properties were previously owned
by Royal Oak Mines and were generally in a state of abandonment
prior to being acquired by Kinross. The reclamation work was
undertaken in accordance with a cooperative agreement between
Kinross and the Ontario Ministry of Northern Development and
Mines.
The Aunor Mine reportedly operated between 1940
and 1984 and consisted of an underground mining operation with
one main shaft as well as two vent raises and sand passes. A
hoist room, mill, shops, storage buildings, office building and
mine dry were located around the headframe along with the
remaining foundations and basements of at least six other
partially demolished buildings. Several of these buildings,
including the mineshaft, presented serious safety concerns and
had to be addressed expeditiously. A town site was also located
west of the mine and housed employees and managers.
Project Details
The 2000 progressive rehabilitation of the Aunor property
consisted of the removal of all buildings and infrastructure
associated with the mine and town site with the exception of one
storage building. The demolition was contracted out to Denison
Environmental Services of Elliot Lake, Ontario.
Well before the demolition work began, Kinross and
the contractor carefully prepared a plan of action that would
see the project come to completion in a 60-day period beginning
September 1, 2000.
In accordance with Kinross and provincial
environmental requirements, maximum recycling and reuse of
building materials was carried out in order to reduce material
volumes transported to a local landfill site. In order to ensure
the success of the recycling program, each house in the town
site was auctioned to private bidders. The successful bidders
were given a finite period of time within which they could
either strip the houses of all reusable building materials,
including plumbing, flooring, cupboards, windows, doors, etc.,
or simply move the entire house. Two of the six houses were
moved from the site and the remaining houses were demolished
after stripping. Similarly, all recyclable materials from the
mine site were separated from the waste streams and collected by
local building material recyclers. Following the removal of all
wastes to the landfill site, all remaining concrete foundations
at the mine site and town site were collapsed and buried in
place as inert fill. All waste chemicals and petroleum products
encountered at the site were gathered and removed by a licensed
waste disposal company. Soils impacted by petroleum hydrocarbons
were excavated and hauled off to a licensed landfill site for
proper disposal. The only remaining building, following the
demolition, was a secured storage facility slated for demolition
within the next two years.
During the demolition of the mine site, the
existing shaft was permanently closed with an engineered
reinforced concrete cap anchored into the shaft collar. The cap
was constructed in accordance with rehabilitation regulations
set out in the Ontario Mining Act.
Following
the removal of all non-recyclable debris, including a former
waste dump on the edges of the mine site, concrete foundations
and brick walls were collapsed into basements and covered with
imported overburden. All roadway surfaces, as well as other
disturbed surfaces on the mine site and within the town site
were loosened up, graded, and prepared for revegetation. The
contractor seeded the prepared areas with a mixture of seed and
fertilizer.
A report describing the progressive rehabilitation
works was issued to the Ministry of Northern Development and
Mines in early 2001. |